Technologies
BBR Worldwide
BBR VT International Ltd
Bahnstrasse 23
8603 Schwerzenbach
Switzerland
Tel  +41 44 806 80 60
Fax +41 44 806 80 50
info@bbrnetwork.com

© Copyright BBR VT

Bridge superstructure

The flyover is a multi-span bridge structure consisting of 12 spans with an overall length of 568 m.

  • Part A: 40 m + 56 m + 56 m + 40 m Total = 192 m
  • Part B: 40 m + 56 m + 56 m + 48 m + 40 m Total = 240 m
  • Part C: 40 m + 56 m + 40 m Total = 136 m

Parts A and C were built using conventional staging over existing median. After stressing the longitudinal BBR CONA 1906 tendons, the strands were coupled using Kcouplers to construct the next span. Part B was carried out using the balanced cantilever method because of the busy traffic at the roundabout and existing Tun Razak flyover. The superstructure consists of two single cell box girders of varying depth from 3.2 m to 2.4 m. The two box girders are structurally independent of each other by a gap of 200 mm. Each box has a 9.45 m deck width, designed to carry two carriageways.

Prestressed diaphragm crosshead on single pier

Due to site constraints and in order to minimize the interference with the existing traffic flow, most of the piers were formed by a single column with a wide crosshead. The prestressed crosshead is capable of carrying two single cell box girders which are monolithically connected to the crosshead. This was made possible by combining the crosshead with the diaphragm. Transverse tendons, consisting of ten BBR CONA 1906 tendons, were provided to transfer the loads from each box girder to the single central pier. This prestressed diaphragm crosshead is also monolithic to the single pier. The top of pier was enlarged into a flare head which is aesthetically pleasing. Such a monolithic connection without bearings also fulfilled the stability requirements in the construction stages of the free cantilevering construction.

Balanced cantilever construction and sharing BBR Network resources

The balanced cantilever method is commonly used for spans from 100 to 250 m – so this case of 56 m span maximum is somewhat unusual. This is possible due to the peculiar circumstances of this project and the availability of travelers lent to us by our Singapore cousins – a very big THANK YOU to them. This is a fine example of the benefits of the international BBR Network – being able to share such resources. In a typical tendon lay-out for free cantilevering construction, the cantilever tendons are usually stressed at one end only, depending on the construction cycle. The anchorages of the cantilever tendons are placed within the deck slab as close as possible to the web. The span bottom tendons are pulled through the ducts after the closure gap and anchored at blisters within the box. The following types of prestressing tendons were used for the Kampong Pandan flyover:

  • Cantilever tendons: BBR CONA 706
  • Span tendons: BBR CONA 1206 and 1906

The construction was so flexible that a mixed construction method was chosen for piers P5 and P8 to speed up the work. The segment on one side was cast on temporary staging, while the segment on other side was completed using form travelers.

Key benefits and advantages

The key benefit of the prestressing technology has been to enable balanced cantilever construction which was a necessity here to ensure that there were no interruptions to the flow of busy traffic at the roundabout and on the flyover.

By combining tendons with form travelers, a flexible method of construction was used to construct the Kampong Pandan flyover in an efficient and timely manner, despite being in the midst of other ongoing projects. The prestressed diaphragm crosshead over a single pier to carry two box girders provided an elegant and effective way to carry the loads to the substructure.